City Subdivision Security in Recent Council Items
A 2023 Public Works report to the Planning Commission explains that Fresno Municipal Code Section 15-3804 requires subdividers to improve or execute a secured agreement to install all the public improvements within a development, and that developers typically post bonds. The Municipal Code text itself could not be read for this page, so the amounts below come from City Council final-map items rather than from code language.
Those items show a consistent shape. Tract 6475 (May 7, 2026) carried $2,885,000.00 for completion and acceptance of the public improvements and $1,442,500.00 for payment security. Tract 6376 (April 23, 2026) carried $7,485,000.00 and $3,742,500. Tract 6383 (March 7, 2024) carried $6,998,000 and $3,449,000, about 49 percent. Tract 6392 (May 22, 2025), where the Housing Authority of the City of Fresno was the subdivider, posted $9,522,390.09 for performance and the same amount for labor and material.
So the observed pattern is payment security at about half of performance security, with at least one case at 100 percent. That is a pattern, not a published City percentage, and the maintenance or warranty security after acceptance and the release rules were not confirmed. The same 2023 report proposed letting the Director defer sidewalks, drive approaches and street trees to home occupancy instead of bonding them; confirm with the City whether that change applies to your tract. For a surety, the combined performance and payment figures are what count against capacity, subject to underwriting and the terms of the bonds issued.
Statewide rules for improvement agreements and security are explained in California subdivision improvement bonds.
The $25,000 Street Work and Excavation Bond
Fresno Public Works Traffic Engineering issues Street Work permits to licensed contractors only. Applicants supply proof of general liability, auto and workers' compensation insurance, a signed Indemnification and Hold Harmless Agreement and a $25,000 Street Work and Excavation Bond, and applications run through Accela Citizen Access.
The bond form (revised November 5, 2024) is written as a continuous, blanket bond in the sum of $25,000 covering permits issued to the principal from time to time under Chapter 13, Article 2 of the Municipal Code. The form states that bonds required by Section 13-206 run for not less than one year, and that no bond may be canceled except on 30 days' written notice to the director. One bond can therefore sit behind many permits, so a contractor that lets it lapse can stall every open job in City streets.
How city and Caltrans permit bonds compare is set out under California encroachment permit bonds.
Street Work Permit Insurance Is Lighter Than Contract Insurance
The City posts an example of insurance requirements for Street Work and Utility permits. The form header reads 2018, so treat it as an example and confirm current limits with the City's Risk Manager. It lists general liability of $1,000,000 per occurrence, $1,000,000 personal and advertising injury, $2,000,000 products-completed operations aggregate and $2,000,000 general aggregate; auto liability of $1,000,000 for any auto; workers' compensation with a waiver of subrogation; and employer's liability of $1,000,000 each accident, disease per employee and disease policy limit.
The endorsement details matter more than the limits. The City must be an additional insured on CG 20 12 04 13, coverage must be primary and noncontributory on CG 20 01 04 13, insurers must be rated A-VII and cancellation requires 30 days' notice. The example states that a certificate of insurance is not acceptable in lieu of the additional insured endorsement, and that the permit is suspended until the City is told required insurance has been restored. A certificate request that arrives without endorsements can hold up a permit.
City Public Works Contract Terms in the 2026 Standard Specifications
Contractors bidding City of Fresno public works face a separate, heavier set of terms. These come from the City's Standard Specifications, Addendum No. 11, approved September 25, 2026. They apply to City contracts, not to subdivision security. The payment bond is for not less than 100 percent of the contract price, the faithful performance bond is for 100 percent and also secures correction of defects, and both must be executed by a corporate surety admitted by the California Insurance Commissioner. The warranty runs one year after completion of the work and restarts on corrected work.
The insurance section raises general liability to $2,000,000 per occurrence, $2,000,000 personal and advertising injury, a $4,000,000 products-completed operations aggregate and a $4,000,000 general aggregate applying separately to the work. Auto is $1,000,000 per accident on Code 1, any auto. Workers' compensation is statutory, with employer's liability at $1,000,000 each accident, disease per employee and disease policy limit. Builders risk at completed value applies to building work, and contractors pollution liability ($1,000,000 each occurrence, $2,000,000 aggregate) applies to remediation, fuel transport and demolition, renovation or MEP work on structures built before 1990.
Insurers must be rated A-VII, the City is added on CG 20 10 (10/01) and CG 20 37 (10/01) and coverage is primary and noncontributory. The contractor also pays Street Work permit fees on City contracts. A GL program built for permit work may need a per-project aggregate or an excess layer to meet these terms, which can vary by carrier guidelines and programs.
The state rules behind public contract bonds are covered in California public works bond requirements.
FMFCD Drainage Fees and CFD Annexation
Storm drainage in Fresno and Clovis runs through a separate special district. The Fresno Metropolitan Flood Control District serves a 399-square-mile watershed with more than 700 miles of pipeline and more than 150 stormwater retention basins, and it states that all final fees are determined by the District before building permits issue or maps are approved, whichever applies. Its own standard plans and specifications govern District facilities. Bond and insurance terms for District facilities were not confirmed for this page, so ask the District early when a tract builds pipe or basin work.
Maintenance can also run through financing districts. In the Tract 6392 item, the subdivider met the maintenance condition by annexing into the City's CFD-11, and the City's Land Development page lists annexation forms for CFD No. 11 (single-family) and CFD No. 9 (commercial, industrial and multifamily). For storm drain and utility contractors, a District-checked basin or line adds an owner to the inspection chain and to the completed-operations exposure.
Coverage for basin, pipeline and outfall work is discussed under insurance and bonds for storm drain contractors.
SEDA and the Region's Growth Projections
On December 18, 2025, the City Council adopted, as amended, the Southeast Development Area (SEDA) Specific Plan, covering about 9,000 acres in Development Area-3 Southeast and Development Area-4 East. The plan anticipates 40,000 to 45,000 dwelling units and 30,000 to 37,000 jobs at full buildout. The plan document notes that the General Plan's buildout numbers include about one third of SEDA's residential capacity, roughly 15,000 units, with the rest after 2035; the posted PDF cover still reads draft, so confirm the adopted version with the City.
Fresno COG's 2023-2060 projections put the county at 1,010,550 residents in 2022 and 1,128,530 by 2060, a gain of nearly 118,000, with the City of Fresno taking the largest share at 55,450 and Clovis adding 30,420. The report anticipates demand for 69,470 new homes from 2022 to 2060, 72 percent of them single-family. It also projects 77,170 new jobs. Much of the land outside city limits falls under County rules, which differ from the City's on security, encroachment and water.
County tract agreements, road permits and well rules are set out on the page for unincorporated Fresno County bond and permit rules.
Assembling a Fresno Program
Start with the jurisdiction. A tract inside the City, one in unincorporated County land and one in Clovis can carry different security forms, maintenance terms and permit rules. For a City tract, ask the City for the performance and payment amounts it expects, confirm whether any deferral applies and plan surety capacity for both figures together. Then line up the $25,000 Street Work bond and endorsement-ready insurance for every contractor touching City streets.
For a City public works bid, compare the 2026 Standard Specifications with your current program before the bid, not after award. Check FMFCD fees and plan check for any basin or pipe, and confirm CFD annexation steps for maintenance. Bonds protect the City; if a surety pays a claim, it typically looks to the principal and indemnitors for repayment. To discuss a specific Fresno project, request a quote or call 844-978-7283.
State licensing, bonding and subdivision rules that apply alongside Fresno's are on the page for California construction insurance and bonding.
Before You Ask for a Quote
What to Gather
- Tentative map conditions and the City's expected performance and payment security amounts
- Any City confirmation of deferral of sidewalks, drive approaches or street trees
- The Street Work and Excavation Bond and its renewal or continuation status
- Additional insured and primary and noncontributory endorsements for each contractor in City streets
- FMFCD fee determination and plan check for drainage facilities
- CFD No. 11 or CFD No. 9 annexation documents where maintenance runs through a CFD
- The City contract insurance and bond sections for any public works bid
What to Ask the Insurer or Surety
- What performance and payment security will the City expect for this tract, and what happens after acceptance?
- How do both securities together affect our surety capacity for the next phase?
- Does our GL meet the $4,000,000 products-completed operations aggregate on City contracts?
- Do our endorsements match CG 20 12, CG 20 01, CG 20 10 and CG 20 37 as the City asks?
- Is contractors pollution liability needed for demolition or MEP work on a pre-1990 structure?
- Will FMFCD require its own bond or insurance for District facilities?
Quick Answer
Recent Fresno City Council final-map items show subdividers posting performance security plus payment security usually at half that amount, with one 100 percent case. Street Work permits typically need a $25,000 blanket bond and endorsed insurance, and City contracts require 100 percent bonds and higher limits.
Common Mistake
Sending a certificate of insurance for a Fresno Street Work permit without the additional insured endorsement, or assuming permit-level limits will meet a City public works contract.
Broker Perspective
In Fresno, separate the tract security, the street permit bond and any City contract terms. Each has its own amount, form and holder. Any one of them can stall a schedule.
Coverage Impact
Subdivision and permit bonds are credit that counts against surety capacity while outstanding. GL limits that satisfy a permit may fall short of City contract aggregates, and pollution may need a separate policy for pre-1990 demolition or MEP work.
Questions Buyers Ask
What percentage does the City of Fresno require for subdivision payment security?
No percentage was confirmed from code text for this page. Recent Council final-map items show payment security at about 50 percent of performance security in three tracts and at 100 percent in a 2025 Housing Authority tract. Ask the City which amounts apply to your map before you approach the surety.
Does one Street Work and Excavation Bond cover more than one Fresno permit?
The City's bond form is written as a continuous $25,000 bond covering permits issued to the principal from time to time. It runs for at least one year and stays in force until canceled on 30 days' written notice. Keep it current, because a lapse can affect every open permit.
Are Fresno permit insurance limits the same as City contract limits?
No. The posted permit example, labeled 2018, lists $1,000,000 per occurrence and $2,000,000 aggregates, while the 2026 Standard Specifications for City contracts call for $2,000,000 per occurrence and $4,000,000 aggregates. Confirm current permit limits with the City's Risk Manager.
When does the flood control district set drainage fees for a Fresno tract?
FMFCD states that all final fees are determined before building permits issue or maps are approved, whichever applies. Its standard plans and specifications govern District facilities. Contact the District early, since the fee and plan check can affect map timing.
How large is the Southeast Development Area?
The SEDA Specific Plan adopted on December 18, 2025, covers about 9,000 acres and anticipates 40,000 to 45,000 dwelling units and 30,000 to 37,000 jobs at full buildout. Much of that capacity is planned after 2035, so phasing and backbone infrastructure will shape when tracts reach the bond stage.
Official Sources
- City Council item 26-520, Final Map of Tract 6475, City of Fresno Legislative Information Center. May 7, 2026: securities of $2,885,000.00 for completion and acceptance of the public improvements and $1,442,500.00 for payment security. Verified 2026-10-25.
- City Council item 26-443, Final Map of Tract 6376, City of Fresno Legislative Information Center. April 23, 2026: $7,485,000.00 for completion and acceptance of the public improvements and $3,742,500 for payment security. Verified 2026-10-25.
- City Council item 24-279, Final Map of Tract 6383, City of Fresno Legislative Information Center. March 7, 2024: $6,998,000 for completion and acceptance of the public improvements and $3,449,000 for payment security. Verified 2026-10-25.
- City Council item 25-641, Final Map of Tract 6392, City of Fresno Legislative Information Center. May 22, 2025: Housing Authority of the City of Fresno as subdivider; $9,522,390.09 for performance and the same amount for labor and material; maintenance requirement satisfied by annexation into CFD-11. Verified 2026-10-25.
- Planning Commission report 23-1122, text amendment to FMC Section 15-3804, City of Fresno Department of Public Works. August 2, 2023: Section 15-3804 requires subdividers to improve or execute a secured agreement; developers typically post bonds; proposed subsection U allowing the Director to defer sidewalks, drive approaches and street trees. Verified 2026-10-25.
- Standard Specifications, Addendum No. 11, City of Fresno Department of Public Works. Approved September 25, 2026; City contracts: payment bond not less than 100 percent and faithful performance bond 100 percent of contract price, admitted surety, one-year warranty, CGL $2M/$2M/$4M/$4M, auto $1M any auto, WC statutory, EL $1M, builders risk, CPL $1M/$2M for pre-1990 work, A-VII, CG 20 10 (10/01) and CG 20 37 (10/01), primary and noncontributory, Street Work permit fees paid by contractor. Verified 2026-10-25.
- Traffic Engineering: Street Work permits, City of Fresno Department of Public Works. Permits issued to licensed contractors only; proof of GL, auto and WC insurance; signed Indemnification and Hold Harmless Agreement; $25,000 Street Work and Excavation Bond; Accela Citizen Access. Verified 2026-10-25.
- Street Work and Excavation Bond form (Rev. 11/05/2024), City of Fresno Traffic and Engineering Services Division. $25,000 continuous bond covering permits from time to time under FMC Chapter 13, Article 2; term not less than one year under Section 13-206; cancellation only on 30 days' written notice to the director. Verified 2026-10-25.
- Insurance Requirements for Street Work and Utility Permit (example), City of Fresno. Form header reads 2018; CGL $1M/$1M/$2M/$2M, auto $1M, WC with waiver of subrogation, EL $1M; CG 20 12 04 13 additional insured; CG 20 01 04 13 primary and noncontributory; A-VII; 30 days' notice; certificate alone not accepted; permit suspended on lapse. Verified 2026-10-25.
- City Council item 25-1641, Southeast Development Area Specific Plan, City of Fresno Legislative Information Center. Adopted as amended December 18, 2025; about 9,000 acres in Development Area-3 Southeast and Development Area-4 East; 40,000 to 45,000 dwelling units and 30,000 to 37,000 jobs at full buildout. Verified 2026-10-25.
- SEDA Specific Plan, City of Fresno. Cover reads draft; General Plan buildout includes one third of SEDA's residential capacity, about 15,000 dwelling units, with the remainder after 2035. Verified 2026-10-25.
- Development in Fresno-Clovis, Fresno Metropolitan Flood Control District. Final fees determined by FMFCD before building permits or map approval, whichever applies; District standard plans and specifications apply; 399-square-mile watershed, more than 700 miles of pipeline and more than 150 retention basins (home page). Verified 2026-10-25.
- Land Development, City of Fresno Department of Public Works. Annexation forms for CFD No. 11 (single-family) and CFD No. 9 (commercial, industrial and multifamily). Verified 2026-10-25.
- Fresno County 2023-2060 Growth Projections, Fresno Council of Governments. County population 1,010,550 (2022) to 1,128,530 (2060), nearly 118,000 gained; City of Fresno +55,450 and Clovis +30,420; 69,470 new units 2022-2060, 72 percent single-family; 77,170 new jobs. Verified 2026-10-25.