California housing finance agencies

California Housing Agencies: CalHFA, HCD and CTCAC Construction Requirements

CalHFA's Insurance Requirements, dated March 28, 2024, set the most detailed construction terms of the three agencies: builder's risk on the completed value with CalHFA as lender's loss payee, general contractor liability ($2,000,000 each occurrence, $4,000,000 aggregate) with CalHFA as additional insured, $5,000,000 auto per accident and deductibles of no more than $50,000. HCD's Uniform Multifamily Regulations and Multifamily Housing Program documents name HCD as loss payee or additional insured and attach state prevailing wage, while CTCAC's regulations set no insurance or bond terms but cap builder overhead, profit and general requirements at 14 percent of construction cost. Bond requirements on a CalHFA loan are set project by project in the loan approval, and each agency updates its documents, so confirm the current year's rules with the agency before pricing the job.

A multi-story wood-framed building under construction, open to weather, with sheathed walls, stacked lumber on the pad and a telehandler alongside

Key Decision Points

  1. CalHFA builder's risk is written on the value of the project at completion, with the coinsurance penalty waived, and a reporting form needs CalHFA's written approval (Insurance Requirements, March 28, 2024, sec. 2.b).
  2. CalHFA is named lender's loss payee by an endorsement at least as broad as form 438BFU NS, and additional insured for ongoing and completed operations on the general contractor's liability policy.
  3. The general contractor carries $2,000,000 per occurrence and $4,000,000 aggregate liability with completed operations for at least 12 months after CalHFA accepts the work, plus $5,000,000 auto per accident.
  4. HCD's Uniform Multifamily Regulations (2017 text) name HCD as loss payee or additional insured and tie the builder fee to CTCAC's 14 percent limit in 4 CCR sec. 10327.
  5. CTCAC's December 11, 2024, regulations exclude builder's general liability insurance from the 14 percent builder fee cap and require related-party general contractors to be audited to the subcontractor level.

Three Agencies, Three Kinds of Requirement

A California affordable housing deal often layers more than one state source. The California Housing Finance Agency (CalHFA) lends, so it publishes an insurance exhibit much like a private construction lender's. The Department of Housing and Community Development (HCD) lends through programs such as the Multifamily Housing Program, and its regulations and standard agreements add loss payee wording and prevailing wage conditions. The California Tax Credit Allocation Committee (CTCAC) allocates tax credits and regulates cost: it caps the builder fee and sets cost certification rules, but its regulations set no insurance or bond terms.

Each agency's document carries its own date, and program rules can change every year. The figures below come from the documents named in each section, so a developer or general contractor typically confirms the current version with the agency, and with the loan documents for its own deal, before a bid or a closing date is fixed. Nothing here means a loan, award or tax credit allocation is assured, or that any contractor qualifies.

CalHFA Builder's Risk and Lender's Loss Payee Terms

Section 2.b of CalHFA's Insurance Requirements for Multifamily Lending and Asset Management, dated March 28, 2024, calls for builder's risk at construction loan closing when CalHFA funds go in during construction. The policy is written on Special Form perils and reaches the structure, materials on and off site and materials in transit. The document states the insurance "shall be provided based on the value of the project at completion," a reporting form needs CalHFA's written approval and the coinsurance penalty must be waived. The borrower and the general contractor carry losses inside the deductible.

CalHFA is named lender's loss payee by endorsement at least as broad as form 438BFU NS, effective at the closing of the acquisition or construction loan, and the insurer waives subrogation against CalHFA. Under section 9, original certificates and endorsements are due before construction loan closing and before construction starts, and coverage stays in force until the final retention payment is released and permanent property insurance is in place. Insurers must be rated A.M. Best A:VII or better (section 1.d).

Flood coverage under section 7.d is the lesser of completed value, the NFIP maximum or the CalHFA loan balance. Under section 7.e, new construction may request an earthquake waiver, and a seismic study may be required to show the probable maximum loss does not exceed 20 percent. How a builder's risk form responds to a given loss depends on its wording and the terms of the policy issued.

CalHFA Liability, Auto and Professional Limits

Section 5 of the same document sets the general contractor's program, and section 3 sets the borrower's. The general contractor's liability policy must name CalHFA "as both additional insured for ongoing operations during any construction and for completed operations." The borrower's liability and auto policies must be primary, with 30 days' written notice of cancellation to CalHFA. Section 1.d lets contractors be insureds under the borrower's policies, or the borrower files separate certificates for each contractor, which is one point where a wrap-up can change the paperwork.

Section 6 extends requirements to architects, engineers and other licensed professionals, and section 8 caps deductibles. Earthquake and flood deductibles can be no more than 5 percent of values per building. Property managers need a $1,000,000 fidelity bond, which belongs to the operating phase rather than construction.

  • General contractor liability: $2,000,000 per occurrence and $4,000,000 aggregate, with products and completed operations for at least 12 months after CalHFA accepts the work
  • General contractor auto: $5,000,000 per accident for bodily injury and property damage, with workers' compensation at statutory limits
  • Borrower liability: $2,000,000 per occurrence and $4,000,000 aggregate on CG 0001, $1,000,000 auto combined single limit and $1,000,000 employer's liability
  • Architects, engineers and other licensed professionals: errors and omissions of $1,000,000 per occurrence and $2,000,000 aggregate, plus the same liability and auto limits
  • Deductibles: property no more than $50,000 per occurrence, and liability and auto no more than $50,000

CalHFA Contractor Qualification and Bonds

CalHFA's Mixed-Income Program term sheet, last revised in February 2025, states that the "General Contractor must be licensed by the State of California." A general contractor new to CalHFA must show three comparable projects built in the past five years, with resumes of its principals, key staff and on-site supervisor. At application, the applicant must show it has engaged a general contractor or construction services firm, and the budget must rest on that firm's preliminary bid estimates, so the contractor's numbers typically feed the loan sizing early.

No CalHFA document read for this page states a general payment and performance bond rule or a completion guaranty percentage. Bond requirements are set per project in the loan approval. A May 2026 staff report for one Mixed-Income project shows that project-level approach: the budget carries a payment and performance bond line, the contract is a guaranteed maximum price, builder overhead, profit and general requirements sit at 6.3 percent against the 14 percent CTCAC limit, and CalHFA's approval of a third-party plan and cost study is a condition of construction loan closing. That project's report also found earthquake and flood insurance not required for that site, which shows how the section 7 terms can turn on project facts.

HCD Uniform Multifamily Regulations: Loss Payee and Builder Fee

HCD's Uniform Multifamily Regulations, 25 CCR sec. 8300 and following, apply across its multifamily lending programs. The text read for this page is the version with an effective date of November 15, 2017. HCD also posts an undated proposed amendment text, and whether those amendments were adopted could not be confirmed, so confirm with HCD that the 2017 text is current.

Section 8303, which addresses scattered-site projects, requires hazard and liability insurance, including flood, for the term of the HCD loan and states that "The Department shall be named as a loss payee or an additional insured on all such policies." HCD receives notice of any lapse or claim. The Multifamily Housing Program standard agreement template for the 2021 round, Exhibit D item 39, repeats that wording for the loan term. The regulations contain no builder's risk or bond section, so those terms come from each deal's loan documents.

Section 8311(c) limits builder overhead, profit and general requirements by 4 CCR sec. 10327, the CTCAC rule below. Section 8311 also sets a cost penalty: a project whose development cost exceeds 170 percent of the limit can draw up to 20 negative points on future HCD funding notices for up to three years, so a general contractor's estimate can carry consequences beyond the current deal.

HCD Multifamily Housing Program: Prevailing Wage and Bond Premiums

HCD's Multifamily Housing Program Final Guidelines, dated May 18, 2023, list as an eligible cost "items intended to assure the completion of construction, such as contractor bond premiums," along with construction-period insurance. The same guidelines state that a sponsor's use of program funds is subject to California's prevailing wage law, Labor Code sec. 1720 and following, and HCD requires a compliance certification before it disburses funds. In the 2021 round standard agreement, Exhibit D item 38, that certification is due before the loan closes and must be signed by the general contractor and the sponsor.

HCD also publishes a generic 2024 HOME loan agreement template for cities and counties that receive HOME funds. In that template the city or county is the lender, HCD's own disclaimer says counsel must customize it, and its construction exhibit shows 100 percent performance and payment bonds and a 10 percent retention on hard costs. Those figures belong to that sample document, not to an HCD rule, and a city or county lender can set different terms in its own agreement.

CTCAC Regulations: Builder Fee Cap, Wage Adjustments and Audits

CTCAC's regulations, 4 CCR sec. 10300 and following, in the version dated December 11, 2024, contain no builder's risk limits, liability limits or payment and performance bond requirement. Their effect on the construction program comes through cost. Section 10327(c)(1) sets "an overall cost limitation of fourteen percent (14%) of the cost of construction" for builder overhead, profit and general requirements, "excluding builder's general liability insurance." Prevailing wages count in the cost base, fixed-price contracts that ignore the limit are barred and payments from the builder to the developer must be disclosed.

Section 10327 also raises the threshold basis limits by 20 percent for a development with a legal prevailing wage requirement, and by an additional 5 percent for a project labor agreement under Public Contract Code sec. 2500(b)(1) or a skilled and trained workforce, with contractors and subcontractors complying with Labor Code sec. 1725.5. Under section 10322(i)(2), cost certification is audited by an independent CPA, and a general contractor that is a related party to the developer must be audited to the subcontractor level.

CTCAC prepared further regulation changes for its December 10, 2025, meeting, including amendments to the cost certification section. Whether that package was adopted, and its effective date, is still to be confirmed, so check the current regulations on the State Treasurer's CTCAC pages before relying on the 2024 text.

Coordinating CalHFA, HCD and CTCAC Terms on One Deal

When CalHFA and HCD both fund a project, each document asks to be named, and the certificates typically show CalHFA as lender's loss payee and additional insured and HCD as loss payee or additional insured, with any other lenders added as their own documents require. The builder fee sits under one 14 percent limit across HCD and CTCAC, while the general contractor's liability premium falls outside it, which can matter when a higher CalHFA auto limit or a longer completed operations term is priced.

A practical step is a single requirements matrix built from the CalHFA exhibit, the HCD regulatory agreement and loan documents and the CTCAC application, checked against the general contractor's current policies and surety capacity before closing. Where a statewide program or a wrap-up is considered, the matrix shows which agency terms each policy has to carry. Coverage terms are subject to underwriting and the terms of the policies and bonds issued, and can vary by carrier guidelines and programs.

Before You Ask for a Quote

What to Gather

  • The current CalHFA Insurance Requirements and the project's CalHFA loan approval or commitment
  • HCD's regulatory agreement, standard agreement and the current Uniform Multifamily Regulations
  • The CTCAC application with the builder overhead, profit and general requirements calculation
  • The general contractor's California license, three comparable projects and key staff resumes
  • Current certificates and endorsements for the general contractor's liability, auto and workers' compensation
  • Builder's risk quote on completed value with loss payee and coinsurance waiver wording
  • Architect and engineer errors and omissions certificates

What to Ask the Insurer or Surety

  • Does the CalHFA loan approval call for payment and performance bonds or another completion assurance?
  • Can the builder's risk carrier endorse CalHFA at least as broadly as form 438BFU NS?
  • Does the general contractor's auto program reach $5,000,000 per accident?
  • Do our deductibles stay at or under $50,000 for property, liability and auto?
  • Is the general contractor a related party, so the cost audit runs to the subcontractor level?
  • Which year's CTCAC regulations and HCD guidelines govern this application?
Quick Answer

CalHFA's March 28, 2024, Insurance Requirements call for completed-value builder's risk with CalHFA as lender's loss payee, $2,000,000 and $4,000,000 general contractor liability with CalHFA as additional insured, $5,000,000 auto and deductibles of no more than $50,000; HCD asks to be loss payee or additional insured, and CTCAC caps the builder fee at 14 percent.

Common Mistake

Assuming a $1,000,000 contractor auto policy meets a CalHFA deal. Section 5 of CalHFA's requirements calls for $5,000,000 per accident from the general contractor.

Broker Perspective

CalHFA wants certificates and endorsements before construction loan closing and coverage kept until the final retention payment is released, so contractor limits and loss payee wording are typically settled while the budget is still being built.

Coverage Impact

CTCAC's 14 percent builder fee cap excludes builder's general liability insurance, so higher agency-driven liability limits typically sit outside the cap, though whether a policy responds to a claim depends on its terms and the facts.

The Same Requirement in Other States

Questions Buyers Ask

What auto liability limit does CalHFA require of a general contractor?

Section 5 of CalHFA's Insurance Requirements, dated March 28, 2024, calls for $5,000,000 per accident for bodily injury and property damage from the general contractor, along with workers' compensation at statutory limits. The borrower's own auto requirement is $1,000,000 combined single limit. Confirm the current document with CalHFA.

Does CalHFA require payment and performance bonds on its construction loans?

No general CalHFA bond percentage was found in its published requirements. Bond requirements are set per project in the loan approval, and one 2026 staff report shows a payment and performance bond line in a project budget. Read the commitment for the specific project.

How must HCD be named on a project's insurance policies?

Section 8303 of the 2017 Uniform Multifamily Regulations text and item 39 of the 2021 Multifamily Housing Program agreement template say HCD shall be named as a loss payee or an additional insured on the hazard and liability policies, including flood, for the term of the loan. Confirm with HCD that the 2017 text is current.

Can Multifamily Housing Program funds pay for contractor bond premiums?

HCD's Multifamily Housing Program Final Guidelines, dated May 18, 2023, list contractor bond premiums and construction-period insurance as eligible costs. The same guidelines attach California's prevailing wage law to the use of program funds, with a compliance certification before HCD disburses.

Does the CTCAC 14 percent builder fee limit include the contractor's liability insurance?

No. Section 10327(c)(1) of the December 11, 2024, CTCAC regulations applies the 14 percent limit to builder overhead, profit and general requirements, excluding builder's general liability insurance. CTCAC prepared later regulation changes, so confirm whether a newer version applies to the application.

What does CalHFA ask of a general contractor it has not worked with before?

Under the Mixed-Income Program term sheet, last revised in February 2025, the general contractor must hold a California license, and a contractor new to CalHFA provides information on three comparable projects from the past five years plus resumes of principals, key staff and the on-site supervisor.

Official Sources

  1. CalHFA Insurance Requirements, Multifamily Lending and Asset Management (March 28, 2024), California Housing Finance Agency. Builder's risk on completed value, reporting form approval and coinsurance waiver (sec. 2.b); lender's loss payee at least as broad as 438BFU NS; additional insured for ongoing and completed operations; borrower limits (sec. 3); general contractor $2,000,000/$4,000,000 liability, 12 months completed operations and $5,000,000 auto (sec. 5); professional E&O and fidelity bond (sec. 6); flood and earthquake (sec. 7); deductibles (sec. 8); timing to final retention release (sec. 9); A:VII rating and contractor certificates (sec. 1.d) Verified 2026-10-26.
  2. CalHFA Mixed-Income Program Term Sheet (last revised February 2025), California Housing Finance Agency. California-licensed general contractor; three comparable projects in five years and resumes for contractors new to CalHFA; engaged contractor and budget from preliminary bid estimates Verified 2026-10-26.
  3. CalHFA Multifamily Staff Report, Sheridan Apartments (final commitment May 20, 2026), California Housing Finance Agency. Project-level example: payment and performance bond budget line, GMP contract, builder overhead, profit and general requirements at 6.3 percent against the 14 percent TCAC limit, plan and cost study as a closing condition, earthquake and flood insurance not required for that site Verified 2026-10-26.
  4. HCD Uniform Multifamily Regulations, 25 CCR sec. 8300 et seq. (effective November 15, 2017), California Department of Housing and Community Development. Sec. 8303 loss payee or additional insured wording for scattered-site projects; sec. 8311(c) builder fee limited by 4 CCR sec. 10327; sec. 8311 development cost penalty; no bond or builder's risk section Verified 2026-10-26.
  5. HCD Multifamily Housing Program Final Guidelines (May 18, 2023), California Department of Housing and Community Development. Contractor bond premiums and construction-period insurance as eligible costs; state prevailing wage law (Lab. Code sec. 1720 et seq.) and compliance certification before disbursement Verified 2026-10-26.
  6. HCD Multifamily Housing Program Standard Agreement Exhibit D (Round 4 template, approved January 11, 2022), California Department of Housing and Community Development. Item 39 HCD as loss payee or additional insured for the loan term; item 38 prevailing wage certification before loan closing signed by the general contractor and the sponsor Verified 2026-10-26.
  7. HCD HOME State Recipient City/County Loan Agreement Template (2024 sample), California Department of Housing and Community Development. Generic city and county sample, to be customized by counsel: 100 percent performance and payment bonds and 10 percent retention on hard costs Verified 2026-10-26.
  8. CTCAC Regulations, 4 CCR sec. 10300 et seq. (December 11, 2024), California Tax Credit Allocation Committee, State Treasurer. Sec. 10327(c)(1) 14 percent builder overhead, profit and general requirements limit excluding builder's general liability insurance; 20 percent prevailing wage and 5 percent project labor agreement adjustments; Lab. Code sec. 1725.5; sec. 10322(i)(2) CPA cost certification and related-party audit to the subcontractor level; no insurance or bond terms Verified 2026-10-26.
  9. CTCAC Final Proposed Regulation Changes, Statement of Reasons (December 4, 2025), California Tax Credit Allocation Committee, State Treasurer. Regulation changes prepared for the December 10, 2025, Committee meeting, including sec. 10322(i); adoption not confirmed Verified 2026-10-26.

Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated

Bring the Contract and the Exhibits.

Share the project, the contract insurance exhibit and any bond or lender requirements. A licensed broker may review them as a courtesy when available, before anything is quoted. See how a project review works or who runs this site.

Full disclaimer about contract and insurance reviews

Contract and insurance reviews are a courtesy service that may be available at times, depending on our workload and on the size, timing and complexity of the project. A review is not guaranteed and is limited to insurance considerations. It is not legal advice and is not a substitute for advice from your own legal counsel, which you may need before signing a contract or obtaining coverage.