Who Sets the Rules for School District Procurement
A.R.S. 15-213 directs the State Board of Education to adopt rules prescribing procurement practices for all school districts. The Board submits proposed rules to the Auditor General, the rules are to be consistent with the state procurement code with the modifications the statute lists, and the Board must conform them to any objection the Auditor General raises. The Attorney General may investigate suspected violations of those rules.
That makes the state rules, not each district's own policy, the starting point for how a school construction job is bid. We could not read those rules for this page: the official Arizona Administrative Code site and the School Facilities Division pages did not load when we checked. This page therefore states only what the statutes say. The bid security percentage, any retention rule in the Board's rules, prequalification steps and insurance minimums should be confirmed in each district's solicitation.
One practical point from the statute does reach every bidder. Subsection A.5 requires the Board's rules to have districts obtain and keep a record of proof that construction providers hold a valid state license, so a current Arizona contractor license in the right classification is part of the bid file on any district job.
For the statewide picture across public and private owners, see Arizona construction insurance and bonding.
Delivery Methods: CMAR, Design-Build, Qualified Select Bidders and JOC
Subsection J has the State Board adopt, and the Auditor General review, rules authorizing districts to procure construction by construction-manager-at-risk, design-build, qualified select bidders list and job-order-contracting delivery. The same subsection says those rules shall not require school districts to obtain bid security for the construction-manager-at-risk method. A CMAR proposer may therefore not need a bid bond, though performance and payment bonds still apply once the construction contract is set.
Job-order contracting has a dollar ceiling. Under subsection M, an individual job order is capped at $1,000,000, or a higher or lower amount the governing board sets in a policy adopted at a public meeting, and requirements may not be divided or fragmented to fit under the cap. Subsection C separately bars dividing or sequencing a project into separate purchases to avoid the limits. A JOC contractor working for more than one district should check each board's policy, because the cap can differ.
When a district awards from a qualified select bidders list, subsection B requires a record of the rationale for the award, made public. Firms seeking to get on those lists should expect their qualifications, safety record and bonding capacity to be weighed, though the scoring itself is set in the district's request.
For how delivery methods compare with other school owners, see K-12 school construction requirements in other states.
The Simplified Program for Work Up to $150,000
Subsection A.2 requires the Board to adopt rules for procurements involving construction not exceeding $150,000, known as the simplified school construction procurement program. Smaller roofing, paving, HVAC and classroom renovation jobs typically fall in this range, and these are often the first district contracts a trade contractor wins.
The simplified program does not drop the bond requirement. Paragraph A.2(c) says a performance bond and a payment bond as required by the section be provided for contracts for construction by contractors. A small contractor bidding its first $90,000 school job should expect to furnish both bonds, which means arranging surety credit before bidding rather than after award.
Subsection B also requires the rules to bar proprietary specifications except under listed conditions. Bidders that see a brand-name specification can ask the district whether an equal is allowed.
Setting up surety credit and insurance for a first public contract is covered in bonding and insurance for public works contractors.
Performance and Payment Bonds Under Title 34
Subsection A.1 of 15-213 requires that surety bonds furnished as bid security and performance and payment bonds be executed and furnished as required by title 34, chapter 2 or 6, as applicable. The applicable chapter depends on the delivery method the solicitation uses.
A.R.S. 34-222 sets the core bond terms. Before the contract is executed, the contractor furnishes a performance bond and a payment bond, each in an amount equal to the full contract amount, binding on award. The bonds must be written by a surety holding a certificate of authority from the Arizona Department of Insurance and Financial Institutions, may not be executed by individual sureties, are payable to the public body and are filed with the body awarding the contract. Each bond includes an attorney fee provision for the prevailing party in a suit on the bond.
The statute also says it is illegal for the invitation for bids, or anyone acting for the contracting body, to require that the bonds be furnished by a particular surety company or through a particular agent or broker. A contractor can use its own surety relationship on district work, subject to that surety's underwriting of the job size, work on hand and the firm's financial statements.
Bond claim notices, deadlines and chapter 6 bonds are explained in Arizona public works bond requirements and payment bond claims.
Retention and Progress Payments in A.R.S. 34-221
A.R.S. 34-221 sets the title 34 rule for progress payments and retention. Monthly progress payments are required on contracts of 90 days or more, and the owner retains 10 percent of each estimate. An estimate is deemed approved seven days after submission unless the owner issues a specific written finding on the disputed items, and certified estimates are paid within 14 days.
When the contract is 50 percent complete, half of the amount retained is paid to the contractor on request if progress is satisfactory and no specific claim requires holding more. After that, no more than 5 percent of later progress payments may be retained, and 10 percent comes back if the owner finds progress is not satisfactory. Retention is paid within 60 days after completion or the filing of a notice of completion, and at the contractor's option the owner accepts substitute securities, including securities of Arizona school districts, in place of cash retention.
We could not confirm whether the State Board's procurement rules adopt this retention schedule for school districts or set their own, because those rules could not be read. Treat 34-221 as the reference point and confirm the retention clause in each district's contract before pricing subcontracts.
Nevada's statute handles retainage differently, as shown for Clark County School District contract requirements.
How the State Funds New School Facilities
A.R.S. 41-5741 says the School Facilities Division administers the new school facilities fund and distributes money at the direction of the School Facilities Oversight Board. The award for new space is driven by a formula. Square feet per pupil is 90 for preschool children with disabilities, kindergarten and grades one through six, 100 for grades seven and eight and, for grades nine through 12, 134 in districts with fewer than 1,800 high school pupils or 125 in districts with at least 1,800.
Cost per square foot is $270.24 for the elementary band, $285.30 for grades seven and eight and $330.30 for grades nine through 12, adjusted annually for construction market considerations, and multiplied by 1.05 for districts in a rural area. As simple arithmetic from those figures, 1,000 net new high school pupils in a large district would support 125,000 square feet at $330.30, about $41.3 million, before any annual adjustment or site-condition change the Board may allow.
A district whose capital plan shows a need for a new school or addition within four years submits the plan on or before September 1, and a district using its own project manager must follow the minimum adequacy requirements in A.R.S. 41-5711. For contractors, a formula budget typically leaves little room for scope growth, so value engineering, allowances and change order pricing tend to get close attention on state-funded schools.
For the Valley's city and county owners that issue permits around new schools, see Phoenix area construction requirements.
What Each District Solicitation Sets
The statutes on this page do not set insurance limits, additional insured wording, contractor prequalification, warranty periods or liquidated damages for school work. Those terms come from each district's solicitation and contract documents, and we did not read a district bid package with enough verified detail to state them here. Expect them to differ between a large urban district and a small rural one.
Before bidding, read the insurance article of the general conditions for limits, additional insured and waiver terms and any owner-controlled insurance program, and match the endorsements on the general liability, auto and umbrella policies to that wording. Coverage terms can vary by carrier guidelines and programs and are subject to underwriting and the terms of the policies issued. Confirm the current requirement with the district.
Before You Ask for a Quote
What to Gather
- The district's solicitation, general conditions and insurance article
- A current Arizona contractor license in the right classification
- Surety letter confirming support for full-contract-amount bonds
- The governing board's job-order contracting policy, if bidding JOC work
- Subcontract forms showing retention, additional insured and waiver terms
- General liability, auto and umbrella policy forms with endorsements
What to Ask the Insurer or Surety
- Which delivery method does this project use, and does it require bid security?
- What job order cap has this district's board adopted?
- What retention clause does the contract use, and does it follow A.R.S. 34-221?
- What insurance limits and additional insured wording does the solicitation require?
- Does the district require contractor prequalification for this project?
- Does the project use an owner-controlled insurance program?
Quick Answer
Arizona school districts procure under State Board rules required by A.R.S. 15-213, with CMAR, design-build, qualified select bidders and JOC allowed, title 34 bonds at the full contract amount and 34-221 retention of 10 percent dropping to 5 percent after half completion.
Common Mistake
Expecting a statewide insurance minimum. The statutes set procurement methods, bonds and retention, but insurance limits and additional insured wording come from each district's solicitation.
Broker Perspective
Because A.R.S. 34-222 bars a district from steering the bonds to a particular surety, agent or broker, a contractor's existing surety relationship typically carries over to school work.
Coverage Impact
Formula-funded budgets under A.R.S. 41-5741 can tighten scope, so builder's risk values and liability limits are worth confirming against the final contract sum.
The Same Requirement in Other States
Questions Buyers Ask
Who writes the procurement rules for Arizona school districts?
A.R.S. 15-213 directs the State Board of Education to adopt procurement rules for all school districts, with review by the Auditor General. Each district's solicitation applies them to a given project.
Do Arizona school districts require bid security on CMAR projects?
A.R.S. 15-213 subsection J says the Board's rules shall not require school districts to obtain bid security for the construction-manager-at-risk method. Performance and payment bonds still apply.
What is the job order cap for Arizona school districts?
An individual job order is capped at $1,000,000 under A.R.S. 15-213, or a higher or lower amount the governing board sets by policy adopted at a public meeting.
How large are bonds on Arizona school construction?
A.R.S. 15-213 sends bonds to title 34, and A.R.S. 34-222 requires a performance bond and a payment bond each equal to the full contract amount, from a surety authorized in Arizona.
How much retention does A.R.S. 34-221 allow?
Ten percent of each estimate, with half released on request at 50 percent completion if progress is satisfactory and no more than 5 percent held after that. Confirm the clause in each district contract.
How does Arizona fund new school buildings?
Under A.R.S. 41-5741, the School Facilities Division administers a fund that pays by square feet per pupil and a cost per square foot set for each grade band, adjusted annually.
Official Sources
- A.R.S. 15-213, Procurement practices of school districts, Arizona Legislature. State Board procurement rules and Auditor General review; title 34 bid security and bonds; simplified program up to $150,000 with bonds; license proof records; CMAR, design-build, qualified select bidders and JOC; no bid security for CMAR; $1,000,000 job order cap; no splitting; proprietary specifications Verified 2026-10-26.
- A.R.S. 34-222, Surety bond required, Arizona Legislature. Performance and payment bonds each equal to the full contract amount; Arizona-authorized surety; no individual sureties; filing; attorney fees; no required surety, agent or broker Verified 2026-10-26.
- A.R.S. 34-221, Contract with successful bidder; progress payments; security, Arizona Legislature. Monthly progress payments; 10 percent retention; seven-day deemed approval and 14-day payment; half released and 5 percent cap after 50 percent completion; reinstatement; substitute securities; 60-day release Verified 2026-10-26.
- A.R.S. 41-5741, New school facilities fund, Arizona Legislature. Division administers the fund; square feet per pupil; cost per square foot by grade band; annual adjustment; rural multiplier; September 1 capital plans; minimum adequacy under 41-5711 Verified 2026-10-26.
Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated